First radioactive sludge removed from Sellafield pond

PE

Milestone in decades-long project to decommission Pile Fuel Storage Pond


Radioactive sludge has been transferred out of the world’s oldest nuclear fuel pond in Sellafield for the first time, a significant milestone in a decades-long programme.

The Nuclear Decommissioning Authority (NDA) said the project is 10 years ahead of schedule and running at half its estimated cost.

Sludge, formed from decaying nuclear fuel, natural growing algae and other debris, has accumulated in the murky water of the Pile Fuel Storage Pond (PFSP) at Sellafield during its 65-year lifespan. Some 300 cubic metres of sludge must be removed so the facility can be safely decommissioned.

The initial sludge removal involves pumping the material into a purpose-built treatment plant next to the pond, before transfer to the drum filling plant. It will take several years to remove all of the sludge in the pond.

The first 500 litre drum containing the mud-like substance was moved to an encapsulation plant last week. It is then grouted – rendering the waste passively safe - and processed into a storage state, ready for final disposal in a geological disposal facility.

The project is being delivered for half the predicted £200 million cost. A 10-year project to dewater the pond will start in 2019, while sludge is still being removed.

The 100-metre long pond was originally used to store nuclear fuel used to make atomic weapons. All the bulk stocks of fuel have now been removed, leaving sludge as the biggest remaining radioactive hazard.

The Pile Fuel Storage Pond (PFSP) is one of the 4 ageing facilities at Sellafield which the NDA has prioritised for clean-up.

John Clarke, NDA’s Chief Executive, said: “The pond was not designed with decommissioning in mind, and therefore we welcome this work by Sellafield to begin safe removal of sludge, which is a key step in making the site safer. The removal of the sludge contributes to achieving our overall goal of risk reduction by placing radioactive material and substances under more modern storage arrangements until it is ultimately moved to a Geological Disposal Facility.”

Sludge accounts for one third of the pond’s remaining radioactive content, after 70% was removed earlier this year with the completion of fuel exports.

Dorothy Gradden, Head of Legacy Ponds for Sellafield Ltd, said: “This is a key moment for our decommissioning mission and another sign of visible progress and one of the first examples of a legacy facility producing a waste ready for a geological disposal facility – it’s a cradle-to-grave solution.”

Share:

Read more related articles

Professional Engineering magazine

Professional Engineering app

  • Industry features and content
  • Engineering and Institution news
  • News and features exclusive to app users

Download our Professional Engineering app

Professional Engineering newsletter

A weekly round-up of the most popular and topical stories featured on our website, so you won't miss anything

Subscribe to Professional Engineering newsletter

Opt into your industry sector newsletter

Related articles