HS2 construction 'should be speeded up'

PE

High-speed rail boss Sir David Higgins proposes accelerated timetable in key report

The boss of HS2 has challenged politicians to pave the way for a faster building of the high-speed line to reduce the £50 billion cost of the project, which is intended to provide a modern link connecting London with Birmingham, Manchester and Leeds.

HS2 chairman Sir David Higgins proposed an accelerated timetable for the northern, phase two, section for the controversial scheme. Launching a report entitled HS2 Plus, Sir David also called for a fresh look at ways of improving connections between phase two and the existing railway.

In addition he proposed a larger development at Euston – the project's southern terminus – but he added that plans to link HS2 with HS1, the London to Kent Channel Tunnel high-speed rail link, should be reconsidered.

Phase one of HS2 would see a line running from London through to Birmingham and is due for completion in 2026.

Phase two will see the line continue in a Y-shape from Birmingham to north-west and north-east England and, under current plans, would be completed around 2032/33.

The current whole-line cost, including contingencies, is £42.6 billion, with £7.5 billion for the trains. Shadow chancellor Ed Balls is concerned about the cost, with other former Labour grandees expressing reservations about the scheme.

Shadow transport secretary Mary Creagh, however, welcomed the report saying: “As always we will continue to hold the government to account for keeping costs down on the project.”

Outlining his report in Manchester, Sir David said reducing the contingencies, which have pushed the total cost of the project up, would be “irresponsible”.

But he said cost cuts might be possible later and he laid down the gauntlet to politicians by saying the speedier the HS2 legislation the better for cost reductions.

Sir David, formerly chief executive of Network Rail, said HS2 was “vital for the future of the country”.

He added: “The cost and impact have to be recognised and acknowledged, but so too do the cost and impact of doing nothing. Without HS2, the people of this country will continue to face the failures of our transport system on a daily basis.”

Sir David said the government should “accelerate phase two as soon as possible”.

This would take the line 43 miles further north than planned, to a new transport hub at Crewe, Cheshire, which could be completed by 2027, six years earlier than planned.

Sir David said the Crewe option was good for the area and the north of England generally, while a “more comprehensive redevelopment” of Euston could see the station become “an iconic driver of local regeneration whose beneficial effects will be felt for generations”.

Sir David said that despite the potential benefits of HS2, he was “conscious of the price – financial, physical and emotional – that HS2 will demand from the country, from communities and from individuals”.

He went on: “That is why I have rejected any thought that the project should cut back on planned mitigation measures, whether noise or environmental. Those will continue. It is also why I support the government's proposed approach to property compensation. We need to be clear about the impact of the project, as well as its benefits, and address the consequences of that impact, as we are.”

Legislation covering phase one is currently going through parliament. Transport secretary Patrick McLoughlin has said that it will not be completed before the general election.

Sir David said: “The uncertainty over the legislative timetable plus the inherent risks associated with any project at this early stage is why I have resisted the temptation to reduce the large contingency contained in the budget. The same approach should be taken to the second phase when the work outlined above is complete.”

But he added: "None of that is to rule out the possibility that a target for a lower budget for phase one could be set at some point in the future, but only when the legislative timetable becomes clearer and more certain. There is a direct connection between the length of time the parliamentary process takes, and the amount of contingency that is required.

“Business people will be concerned that this part of the development has been put on hold.”

Malcolm Dowden, consultant at Charles Russell LLP, commented: “Sir David Higgins makes some extremely strong points about the potential economic benefits of an accelerated construction programme, particularly in terms of rebalancing the UK economy and reducing the dominant role of London and the south-east.

“However, it is unlikely that the current legislation could be extended without fatally slowing its progress, as HS2 requires parliamentary approval and the legislation that is due for its second reading in late April could not easily be amended to authorise the northern elements of HS2. Second reading approves the principle of a Bill and in this case, it also opens the period during which property owners and others affected by the scheme may petition parliament.”

Sir David acknowledged: “HS2 is an enormous undertaking, but it is not an end in itself. If we do it right, it can be a catalyst for fundamental change at both a local and national level, up and down the country.

“It is ambitious because it needs to be, to meet the demands not just of the here and now, but of the future.”

Business secretary Vince Cable expressed support for Sir David's phase two plans, while the Institution of Civil Engineers and the CBI were among other groups that received the report warmly.

However, anti-HS2 groups cast doubt on the possibility of bringing forward the phase two work, while the revamped Euston plan was seen as merely bringing “more wealth and work into London”.

Joe Rukin, campaign manager for Stop HS2, said: “David Higgins has spent three months looking for cost savings for HS2 and he hasn't found a single bean. Any pretence that the costs of HS2 are under control are a fraudulent attempt to con the public.”

He added that the £50 billion cost was “always too low, and represents the cost if the whole project was built in one year and that year was 2011”.

He went on: “We know that these costs will continue to escalate. The only answer is to cancel the project and go back to the drawing board right now.”

Under the accelerated plan put forward by Sir David, the Manchester leg of phase two could be completed by the end of March 2030, with the Leeds leg finished by the end of June 2030.

He added that phase one could be operational by Christmas 2026, while his redevelopment vision for Euston would require relocation of certain existing rail services during constructions.

Sir David said that constructing the London stage of the project represented HS2's “biggest challenge”. In addition, decisions would be needed on London commuter connections and a link between the West Coast main line and the cross-London Crossrail scheme.

John Longworth, director-general of the British Chambers of Commerce said HS2 would “only reach its true potential if it is a fully-functioning national network, which includes linking it to HS1”. 

Share:

Read more related articles

Professional Engineering magazine

Current Issue: Issue 1, 2025

Issue 1 2025 cover
  • AWE renews the nuclear arsenal
  • The engineers averting climate disaster
  • 5 materials transforming net zero
  • The hydrogen revolution

Read now

Professional Engineering app

  • Industry features and content
  • Engineering and Institution news
  • News and features exclusive to app users

Download our Professional Engineering app

Professional Engineering newsletter

A weekly round-up of the most popular and topical stories featured on our website, so you won't miss anything

Subscribe to Professional Engineering newsletter

Opt into your industry sector newsletter

Related articles